Home / Landscaping / Resource Center / Irrigation System Care
Irrigation System Care
Winterization Procedure Outline
- Shut off irrigation system ball valve and/or curb stop. (If
additional shut-off is within building shut this valve off ). Also
at this time shut off the #2 ball valve on the DCVA.
- Start air compressor and let idle with air valve open on
compressor.
- Connect air compressor assembly to irrigation stub-out,
downstream of the DCVA. Be sure that gate valve is shut
off on air compressor assembly.
- Manually open one valve, this should remain open through-out
the entire operation.
- Slowly open air compressor assembly gate valve and energize the
system, be sure that air pressure doesn't exceed 80
psi max., 60 psi is the normal pressure range.
- Let each zone run until only air vapor is coming out of
sprinkler heads.
- Activate the next zone by the irrigation controller. After
going through each zone then repeat the process a second time to
insure that each zone is fully evacuated.
- Shut off air compressor gate valve and remove from system, but
do not shut compressor down.
- Go to DCVA, open all test cocks, open irrigation system ball
valve while leaving the #2 ball valve on the DCVA closed.
- Place air compressor assembly on the #1 test cock and blow
through the DCVA, water in the pipe to the building and also in the
DCVA will be evacuated.
- Then proceed to place the air compressor assembly on the
remaining test cocks one at a time until all water is removed from
the unit.
- Close all test cocks, shut off irrigation ball valve, leave
DCVA ball valves open at 45' angle.
- Replace cap on irrigation blow out stub.
- Close the valve that was opened manually after air in the
system has evacuated.
- Turn controller to the off position and leave plugged in
Sprint Start-up Procedure Outline
- Close all drain valves, automatic control valves, that may have
been manually opened during the winterization process and all hose
bib assemblies.
- Close the petcocks on the backflow device, which may be one of
the following; PBVA, DCVA or RPBA.
- Locate the main water supply meter or point of connection and
turn on very slowly.
- Open the ball valves on the backflow device to energize the
mainline. These should be opened slowly.
- If your controller is equipped with a alkaline battery, it
should be replaced at this time. If the controller was left plugged
in over the winter months, simple check current programming, make
whatever adjustments are necessary and proceed to step 6. If the
controller was unplugged over the winter months, it may need to be
reprogrammed.
- Run through the enitre system to assure proper working
conditions and to check for leaks or repairs that may need to be
addressed.
- Place controller to the on position and monitor the system to
ensure that adequate watering is provided for various planting
mirco zones.